Port Shore-Power & Distribution — Burgas Marine Terminal

Shore-power pedestals, HV cable distribution, and cold-ironing infrastructure for a Burgas Black Sea marine terminal.

2024Year
MIG designed and installed the electrical distribution infrastructure for a new marine terminal at the Port of Burgas, including a 10 kV underground cable ring feeding six quay transformer stations and shore-power distribution pedestals at each berth.
Shore-power (cold-ironing) infrastructure was installed in accordance with IEC/IEEE 80005-1 to allow berthed vessels to switch from diesel generators to grid power, reducing emissions in the port area. The system supports 6.6 kV and 440 V vessel connections with automatic frequency synchronisation.

Project Milestones

Q1

Design & Engineering

Feasibility study, schematic design, permit submission, and equipment specifications finalised.

Q2

Manufacture

Factory assembly of switchgear panels, transformer station enclosure, and cable management systems.

Q3

Site Installation

Civil works, equipment delivery, installation of primary and secondary systems, cable termination.

Q4

Commissioning & Handover

High-voltage testing, protection relay settings, grid connection approval, and client handover.

Project Location

Bulgaria