110/10 kV Transformer Substation — Plovdiv Industrial Park
Design, supply, and commissioning of a new 110/10 kV primary substation serving a 35-hectare industrial park with 40 MW connection capacity.
Project Milestones
Design & Engineering
Feasibility study, schematic design, permit submission, and equipment specifications finalised.
Design & Engineering
Feasibility study, schematic design, permit submission, and equipment specifications finalised.
Manufacture
Factory assembly of switchgear panels, transformer station enclosure, and cable management systems.
Manufacture
Factory assembly of switchgear panels, transformer station enclosure, and cable management systems.
Site Installation
Civil works, equipment delivery, installation of primary and secondary systems, cable termination.
Site Installation
Civil works, equipment delivery, installation of primary and secondary systems, cable termination.
Commissioning & Handover
High-voltage testing, protection relay settings, grid connection approval, and client handover.
Commissioning & Handover